DTS is currently working on a multi-year project to upgrade our schools’ wireless networks.

Updates

  • 10/16 Surveys complete. Waiting for reports and suggestions on problematic areas

 

Elementary Schools

Status School Site Survey Wiring Conversion Notes
Status: Complete Alpine Elementary School Complete Complete
6/21
Status: Complete Black Rock Elementary School Complete Complete  7/24
Status: Complete Blue Mountain Elementary School Complete Complete 8/9
Status: Complete Burlington Elementary School Complete Complete 8/22
Status: Complete Centennial Elementary School Complete Complete  7/26
Status: Complete Central Elementary School Complete Complete  8/14
Status: Complete Columbine Elementary School Complete Complete 8/11
Status: Complete Eagle Crest Elementary School Complete Complete 8/9
Status: Complete Erie Elementary School Complete Complete  7/24
Status: Complete Fall River Elementary School Complete Complete  7/17
Status: Complete Hygiene Elementary School Complete  Complete  7/12
Status: Complete Indian Peaks Elementary School  Complete Complete  7/20
Status: Complete Legacy Elementary School  Complete Complete  7/21
Status: Complete Longmont Estates Elementary School  Complete Complete  7/20
Status: Complete Lyons Elementary School  Complete Complete  7/12
Status: Complete Mead Elementary School  Complete Complete  7/11
Status: Complete Mountain View Elementary School Complete Complete  7/27
Status: Complete Niwot Elementary School Complete 8/7 – 8/11 8/28
Status: Complete Northridge Elementary School Complete 8/2 – 8/4 8/15
Status: Complete Prairie Ridge Elementary School Complete 8/4 – 8/10 8/11
Status: Complete Red Hawk Elementary School Complete Complete  7/26
Status: Complete Rocky Mountain Elementary School  Complete Complete 8/10
Status: Complete Sanborn Elementary School  Complete 7/10 – 7/14  7/25
Status: Complete Spark! Discovery Preschool  Complete Complete  7/21

*Scheduling with Principal

Middle Schools

Status School Site Survey Wiring Conversion Notes
Status: Complete Altona Middle School Complete Complete
6/21
Status: Complete Coal Ridge Middle School Complete Complete  6/15
Status: Complete Erie Middle School Complete 6/26 – 6/30  7/14
Status: Complete Longs Peak Middle School Complete Complete  6/16
Status: Complete Mead Middle School Complete 7/3 – 7/7  7/13
Status: Complete Sunset Middle School Complete Complete  7/14
Status: Complete Trail Ridge Middle School Complete Complete 7/17
Status: Complete Westview Middle School Complete 7/10 – 7/18  7/18
Status: Complete Thunder Valley K8 School  Complete Complete 6/14
Status: Complete Timberline PK8 School Complete  Complete 7/18

High Schools

Status School Site Survey Wiring Conversion Notes
Status: Complete CDC/Olde Columbine High School  Complete Complete Complete
Status: Complete Erie High School  Complete  Complete Complete Auxiliary gym: Partial Coverage
Status: Complete Frederick High School  Complete  Complete Complete Auxiliary gym: No Coverage
Status: Complete Longmont High School  Complete Complete Complete Auxiliary gym: Partial Coverage
Status: Complete Lyons Middle/Senior High School  Complete  Complete Complete Auxiliary gym: No Coverage
Status: Complete Mead High School  Complete  Complete Complete
Status: Complete Niwot High School  Complete  Complete Complete
Status: Complete Silver Creek High School  Complete Complete  Complete Auxiliary gym: No Coverage
Status: Complete Skyline High School  Complete  Complete  Complete Auxiliary gym: No Coverage

Admin Building

Status Building Site Survey Wiring Conversion Notes
Status: Complete Clover Basin ESC Complete Complete
Complete
Status: Complete East Bus Terminal Complete Complete 7/27
Status: Complete Education Service Center Complete Complete 6/23
Status: Complete Lashley ESC Complete Complete  7/27
Status: Complete Learning Services Center Complete Complete 6/23
Status: Complete Lincoln ESC Complete Complete 5/31
Status: Complete Main Street School Complete Complete  7/20
Status: Complete Student Services Complete Complete 6/2

 *Tentative Schedule


Statuses

Status: Complete School’s upgrade to the new wireless standard is complete. Some cleanup work may still be required.
Status: In Progress School’s upgrade to the new wireless standard is in progress. Work being done at the school may have some affect on normal school operations.
Status: Pending School is operational on the district’s previous wireless standard. Any work being done at the location has little to no affect on normal school operations.

Site Survey – Each site has to be mapped for proper placement of wireless access points. Many factors affect placement including room geometry, wall building materials, relationship to other access points, etc.

Wiring – The new wireless will provide a much deeper saturation of access. This increased access requires almost four times as many access points as the previous system. There for DTS has to install almost three times as much wiring.

Access Points Live – Due to interference the old and the new wireless cannot be turned on at the same time. After the wiring is complete a small number of new access points will be installed but not activated. When these are ready and in coordination with building administration the old wireless will be turned off.  At this point, much of the building will lose wireless access completely. Again in coordination with building administration, the rest of the access points will be installed and activated to make wireless available across the building in stages. Graph show percentage of building live on new wireless.

Completed – The date when the school was completely live on the new upgraded wireless.


Personal Devices Impact:
The new wireless network operates at the 5GHz frequency. Some personal devices that operate at the lower 2.4GHz frequency will not be able to connect to the new wireless network. Please make sure all future personal technology choices have the ability to operate at the higher 5GHz frequency if connecting to the district’s wireless network is important to you.